President Bola Tinubu has ordered the redesign and total reconstruction of the Benin-Agbor-Asaba road and other major federal highways across Edo State and adjoining corridors, as the Federal Government moves to tackle worsening road conditions that have disrupted transportation, damaged vehicles and increased the cost of doing business nationwide.

The directive came on Tuesday as the Minister of Works, David Umahi, inspected the troubled Benin-Agbor-Asaba road in Edo State, while the Minister of State for Works, Bello Goronyo, visited the Ifaki-Oye-Kabba and Efon-Iwaraja roads in Ekiti State, where motorists and residents have endured prolonged delays and hardship.

Umahi apologised to commuters and took responsibility for the condition of the Benin-Asaba road, while condemning the concessionaire handling its reconstruction. He ordered steps towards the total reconstruction of the highway, stressing that palliative works would not be sufficient to resolve the problem.

The Benin axis of the Benin-Agbor-Asaba road is in a terrible state, though the gridlock of the past two weeks on the road had eased.

Further findings in other parts of the country revealed that federal roads were in dilapidated state.

Some of them are Ibadan-Abeokuta, Lagos-Badagry and Ibadan-Ife-Ilesa in the west; Onitsha-Enugu, Enugu-Abakaliki, Onitsha-Owerri and major federal highways in the east; East-West Road, Warri-Sapele, Benin-Sapele and others in the south south.

Abuja-Kaduna, Abuja-Lokoja, Lokoja-Okene and inter-state routes are also in a bad state in the northern part, as well as Kaduna-Kano, Kano-Katsina, Sokoto-Gusau

Maiduguri-Damaturu, Bauchi-Jos, Gombe-Yola roads and other strategic routes.

Blame game

Umahi, while on an on-the-spot assessment of the Benin-Asaba road following public outcry over its worsening condition, condemned the Benin-Asaba Expressway Concessions Company over what he described as the poor handling of the Benin-Asaba highway.

The expressway was concessioned to BAECC in 2025 for reconstruction and expansion from four to 10 lanes.

The company had, in October last year, said it would complete the 10-lane highway within the stipulated timeframe.

However, Umahi said the concessionaire ought to have been arrested for destroying public property, accusing the company of manipulating the process to secure the contract.

He said, “I commend Governor Monday Okpebholo for his intervention in lots of federal roads across the state. He is not saying this is a federal or state road. I apologise to commuters plying this road. The NDDC is willing to intervene. I am disappointed with the concessionaire. I take full responsibility for their misdeed and destruction of public assets.

“The Ministry of Works does not allow removal of asphalt. We begged them not to remove it. The concessionaire should have been arrested for destroying public property. This road was not like this when it was handed over. I am instructing the ministry to arrest any concessionaire that removes asphalt from existing roads.”

Addressing the Chief Executive Officer of BAECC, Samuel Daramola, Umahi accused the company of manipulating the process to secure the contract and questioned its technical capacity to handle the project.

He said, “You manipulated the process to get the job. You have no knowledge of road construction. You don’t know what you are doing. You have no technical staff or competence.

“The President has directed us to do whatever is possible to fix this road. The law is there and there is overriding public interest. It is also the fault of the government for not finding out the competency of concessionaires. You are learning how to do construction on our road. This is dangerous.

“This is provocation at its highest level. It is a pity when people cannot pass the road. We have competent contractors who we will beg to restore the road. We will be asking CCETC to fix the bad spot in Asaba.

“I am disappointed. The President has directed me to redesign all roads from Kogi to Warri and around Edo State. They are to be done with concrete pavement. We need total reconstruction of this road and not this palliative.”

On his part, the BAECC CEO blamed heavy rainfall and heavy vehicular traffic on the highway for the slow pace of work.

He said the volume of traffic had made it difficult for the company to construct side drains while keeping the road open to motorists.

He said, “We expanded the road to eight lanes. We did palliative work for some months. We are wrestling with weather as much as we want to keep to the scope of work. We expected our palliative work to have been completed long ago.

“We have to choose between doing side drains and combating heavy traffic. We are compelled to open the road when it was not ready. We have to do the work over again. This is a concession road and we are funding this road with our money.

“How do we start with drains when there is heavy traffic? We have tried to engage all parties and communities. We are determined to ensure we complete this road. We have a reputation to maintain.”

The representative of the project consultant, Toyin Akinlapa, said BAECC failed to heed instructions to execute the project according to specifications.

He said, “The concessionaire did not heed our instruction. We told them to first do the drains but they ignored us and that affected the road. The company had some challenges in their technical team.”


Works Minister, David Umahi

The Chairman, House Committee on Works, Akin Alabi, who was part of the inspection team, urged President Bola Tinubu to review the agreement with the concessionaire.

Discover more
Governor
Government’s
Latest news headlines
Featured news articles
News website monetization
He said, “We should review all such contracts. We cannot afford concessionaires who will give us issues. The people want to see good roads. There must be palliative measures. Let us come up with a solution where people can move.”

Also, Senator Allwell Onyesoh described the condition of the Benin-Asaba highway as despicable.

Governor Monday Okpebholo said the prompt response by President Tinubu demonstrated his concern for the plight of the people, urging residents not to listen to opposition comments on social media.

Commuters, residents groan

Meanwhile, motorists and commuters have continued to count their losses as the deteriorating condition of the Benin-Asaba road disrupts businesses, livelihoods and movement along the route.

A driver who plies the road, who identified himself simply as Chukwudi, said the contractor should have concentrated on one side of the road while leaving the other open to traffic, rather than grading both sides simultaneously.

“Now, the situation is so bad,” he lamented.

A resident, who spoke on condition of anonymity, decried his ordeal on the road.

“It’s been difficult for me because I use this road every day because of the business I do. Imagine sleeping on the road or wasting over five to 12 hours at one spot. It’s unimaginable, I must tell you,” he said.

Businesses suffer

The deteriorating condition of the road, particularly around the bypass, has forced some shops to close, while hawkers have lamented poor sales since rainfall rendered parts of the route almost impassable.

One of the traders at the bypass, Stella, said the bad road had resulted in flooding whenever it rained, making business difficult.

She said she had to wade through the flood to sell her wares and earn money to support her family, while taking care not to fall into the muddy water.

She said, “Generally, business has been very bad, especially on days when it rains. However, I made some money on those days when the gridlock was at a standstill. My appeal goes to the government to ensure the contractor sticks to the terms of engagement.”

Another resident, Chris, said, “I have not been able to do business for a while because transportation is high, and I use commercial motorcycles most of the time due to the gridlock. It’s been difficult. My hope is that the government will come to our aid. It is not enough for the minister to inspect the project; he must ensure the work is done,” he said.

Fuel cost

For motorists travelling between Asaba and Benin, the journey is no longer measured only in kilometres, but in hours spent in traffic, fuel consumed, vehicle repairs, lost business and rising prices. What was once a relatively straightforward trip has become a daily struggle for drivers, traders and passengers who depend on the route.

For Nobel Akanuibiam, a regular driver on the route, the deterioration is clear. He said the journey from Second Junction in Benin City to Summit Junction in Asaba used to take about one-and-a-half hours but now takes up to five hours.

Related News
FAAN faces backlash over N30,000 airport taxi fare
C’River APC launches support group for gov, Tinubu
Mass presence of govs in off-cycle elections
“Before now, travelling from Asaba to Benin, or from Benin to Asaba, was much easier. From the Second Junction in Benin to Summit Junction in Asaba, the journey could take about one and a half hours. Today, that same journey can take up to five hours. That’s about three and a half hours longer than before, simply because the road has deteriorated so badly,” he said.

The longer journey has also increased his fuel expenses. Nobel said he recently spent about ₦45,000 on fuel, compared with the ₦20,000 to ₦25,000 he previously spent.

“Now, when traffic is blocked and you spend three or four extra hours on the road, your fuel consumption increases significantly. What might normally take about 15 litres can become much more because the vehicle is constantly moving slowly, stopping and starting,” he said.

He also complained of frequent vehicle repairs, saying ball joints, shock absorbers and other components now require attention more often.

“Instead of taking the vehicle to the mechanic once a month for routine servicing, you may find yourself going almost every week because of damage caused by the road,” he said.

The delays have also reduced the number of trips drivers can make, while some motorists and passengers spend nights around difficult sections or avoid travelling at night because of security concerns.

For heavy-duty vehicles, the situation is equally costly. A trailer driver, Abre, said the road had increased fuel consumption and operating costs.

“When the road is free, the journey should not take more than about three hours. But because of the bad road and the traffic, we spend much longer on the journey,” he said.

The impact extends beyond motorists to traders and consumers. A fruit seller in Asaba who regularly travels to Onitsha said a journey that used to take about 30 minutes now takes an hour or more.

“When we spend more time on the road, we also spend more money on transportation,” she said.

She said transport costs had risen to about ₦1,500 on a particularly congested day, forcing her to increase the prices of her goods.

“I have had to increase my prices because transportation and other expenses have gone up. When transportation becomes more expensive, everything else becomes more expensive,” she said.

The experiences of the drivers and trader show how the road crisis has become an economic burden. Longer journeys mean higher fuel and maintenance costs for motorists, while traders pass increased transportation expenses on to consumers through higher prices.

The crisis, therefore, extends beyond the road, affecting businesses, livelihoods and household budgets as motorists, traders and consumers continue to bear the cost of deteriorating infrastructure.

Goronyo visits Ekiti

The Minister of State for Works, Bello Goronyo, on Tuesday also visited Ekiti State to inspect the condition of some federal roads and assess the hardship faced by motorists and commuters.

Goronyo visited the Ifaki-Oye-Kabba Road, where road users groaned over a badly damaged section around Oye-Ekiti, leaving articulated vehicles stranded for days. He expressed concern over the hardship caused by the impassable portion.

An articulated vehicle driver, Quasm Abudu, said he had been stuck at a particular spot on the highway for about three days, lamenting the hardship and business opportunities lost while stranded.

A resident of Oye-Ekiti, Bolade Olowo, described the condition of the road as “traumatic and unpalatable,” saying its continued deterioration was crippling socio-economic activities and cutting off communities along the route.

He added that the poor road condition also posed a serious security threat, urging the Federal Government, the state government and other relevant agencies to urgently mobilise resources to fix it.

Olowo said the road links Ifaki, Oye, Ayegbaju, Ilupeju, Itapa and Osin-Ekiti, communities that depend heavily on the route for economic activities and the movement of goods to other parts of the country.

Speaking at the damaged section, where emergency palliative work had commenced to free stranded trucks and restore access, Goronyo reiterated the Federal Government’s commitment to rehabilitating the Ifaki-Oye-Kabba Road.

He described the route, which links the South-West to the northern part of the country, as a critical economic corridor requiring urgent intervention. He disclosed that the rehabilitation contract was awarded to Gamji in 2025.

According to him, the contractor had been mobilised but complained of inadequate funding, prompting the Federal Government to review the funding arrangement to ensure its return to site.

Goronyo said immediate intervention had also commenced through the Federal Road Maintenance Agency, with equipment and materials deployed to the affected section.

“We want to appeal to all the people concerned to be patient with us. We will make sure that we put this road to use very, very soon,” he said.

Appealing to agitated motorists, the minister said the emergency work was expected to make the road passable within 48 hours.

He added that the entrance from the Ifaki end would be blocked to prevent articulated vehicles from using the road until the palliative work was completed.

Goronyo also inspected the Efon-Iwaraja Road, where motorists were forced to turn back and seek alternative routes because of a deep failed section.

He promised immediate remedial work, assuring residents and motorists that the Federal Government would not allow the road to remain impassable.

“I am assuring residents and motorists that the Federal Government will undertake immediate remedial work on the Efon-Iwaraja Road to restore access and ease the hardship being experienced by road users,” he said.

The minister said the interventions were part of President Bola Tinubu’s directive to address critical road failures across the country and ensure the free flow of traffic.

He listed ongoing major road projects by the administration to include the approximately 1,068km Illela-Sokoto-Badagry Highway, the 750km Lagos-Calabar Coastal Highway and the Abuja-Kaduna-Kano Road.

Goronyo said massive investment in road infrastructure was necessary because roads were central to economic activities, security, employment, agriculture and healthcare.

“Roads lead to prosperity,” he said.

Reiterating the government’s determination to complete ongoing projects and use improved road infrastructure to stimulate commerce, industry, employment and food security, Goronyo said the administration was committed to addressing the country’s road infrastructure deficit.

“For the past one week, the Minister of Works, David Umahi; myself; all the directors in the ministry, all the SAs and SSAs of Mr President, we have been crisscrossing the roads across the country.

“We have met a very difficult situation and we are fixing it,” the minister said.

Zaria Road reconstruction

Ongoing reconstruction along the Zaria Road corridor in Kano State has caused traffic congestion, with motorists and commuters experiencing delays along the affected stretch.

The work is being carried out from the Ado Bayero Flyover, popularly known as Gadar Lado, towards Unguwa Uku Motor Park.

The affected section is estimated at about 1.5 kilometres, although the extent may change as construction progresses.

The reconstruction has narrowed the available carriageway, slowing traffic and causing significant build-up, particularly during peak periods.

The development has raised concerns among motorists and commuters who depend on the busy route, which connects several parts of Kano metropolis.

Further details on the project, including its cost, contractor, duration and expected completion date, are yet to be established.

Courtesy punchonline

Continue Reading
Click to comment

Leave a Reply

Your email address will not be published. Required fields are marked *

News

US insists Nigeria must remain Country of Particular Concern

Published

on

The United States government has insisted that Nigeria should retain its Country of Particular Concern, CPC, designation, saying the country has not done enough to protect Christians from attacks.

Assistant Secretary of State for African Affairs, Frank Garcia, made this statement on Thursday during a congressional hearing on violence in Nigeria.

Garcia was responding to questions from US Congressman Riley Moore, who asked about the government’s efforts to dismantle militia strongholds and kidnapping camps in the Middle Belt, particularly in Benue and Plateau states.

Moore also raised concerns over the exclusion of the states from the forest guard initiative and delays in deploying 1,000 approved guards to Plateau.

“Before you answer that, we cannot take this CPC designation off of this country. They have not done enough,” Moore said.

Garcia acknowledged the lack of progress, but said Nigeria was taking steps to address the concerns, although they had yet to produce results.

He said the country’s security capacity was still being developed and that deployments were not happening fast enough.

“Unfortunately, the violence has not stopped,” Garcia added, citing continued attacks in Kaduna and Plateau states.

He said the US had provided police training and equipment, expanded intelligence sharing and worked with Nigerian financial institutions to disrupt terrorist financing.

Garcia added that Washington would continue diplomatic engagements and security cooperation to protect vulnerable communities and ensure accountability.

However, the Nigerian government has consistently rejected claims of a “Christian genocide” or targeted religious persecution, maintaining that insecurity affects Nigerians of all faiths.

Continue Reading

News

Cooking Gas price goes up to N1,800/kg

Published

on

Liquefied Petroleum Gas, commonly known as cooking gas, has risen significantly, forcing Nigerians to spend more to purchase the product.

The increase comes as depot owners and retailers raised their prices over the past two days.

StockGap increased its depot price by N25 to N1,440 per kilogram. Nigerian Independent Petroleum Company Limited, NIPCO, Mobil (now 11 Plc) and Ardova, on the other hand, sold the product at N1,400 and N1,390 per kilogram, respectively.

Similarly, LPG retail outlets, including Raniol, Juda Oil and Nigerian National Petroleum Company Limited, NNPC, outlets in Abuja and its environs, now dispense cooking gas at between N1,550 and N1,600 per kilogram, up from N1,400 and N1,500.

Micro-LPG dealers sell the product for between N1,700 and N1,800 per kilogram, depending on the location in Abuja.

Earlier, NIPCO’s spokesperson, Taofeek Lawal, had exclusively told DAILY POST that LPG prices could increase further between November and January next year.

The latest price increase means that Nigerians who previously spent N17,500 to refill a 12.5kg cylinder at N1,400 per kilogram will now pay N20,000 at the new rate of N1,600 per kilogram, representing an additional N2,500.

Continue Reading

News

2027: Tinubu Must Withdraw ‘All Is Fair in Politics’ Remark, Embrace Peaceful Coexistence — ADC-PCC

Published

on

The African Democratic Congress Presidential Campaign Council (ADC-PCC) has called on President Bola Ahmed Tinubu to publicly retract his controversial “All Is Fair in Politics” remark, warning that such rhetoric fuels political division, emboldens thugs and poses a grave threat to the nation’s peace and stability.

The ADC-PCC also expressed concern over what it described as the President’s disturbing silence on the conduct of some APC governors and party chieftains who have openly made inflammatory statements and allegedly encouraged political violence.

In a statement signed by its Director of Media and Publicity, Kola Ologbondiyan, the ADC-PCC urged President Tinubu to rise above partisan interests and demonstrate the statesmanship expected of a national leader, citing former President Goodluck Jonathan’s unequivocal declaration that no presidential ambition was worth the blood of any Nigerian.

The Council described as shocking the President’s failure to condemn the growing wave of political violence, noting that, through his spokesman, Mr. Bayo Onanuga, the Presidency had instead chosen to caution opposition parties while shielding those allegedly responsible for violence within the ruling APC.

“President Tinubu cannot claim to desire peace when his own words provide cover for violence.

“‘All Is Fair in Politics’ is not the language of a Head of State. It is the language of political desperation and an open licence for thuggery, ballot snatching, intimidation and bloodshed.

“From Edo to Cross River, Gombe to Lagos, and Kebbi to Kaduna, Nigerians have witnessed attacks on opposition gatherings, destruction of campaign materials and the brutalisation of innocent supporters, allegedly by APC-sponsored thugs.

“Yet, Mr. President has not considered it necessary to call his governors and party members to order.

“Instead, the Presidency has resorted to diversionary tactics, blaming victims and preaching restraint to the opposition while members of the ruling party are accused of unleashing violence across the country,” the statement said.

The ADC-PCC challenged President Tinubu to explain why his condemnation of political violence appears directed at the opposition rather than members of his own party.

It asked: “Why has Mr. President refused to condemn APC governors who openly threaten opposition supporters? Why has he remained silent over public incitement by officials of his party? Why is his anger always directed at the opposition and never at those within his own political fold?”

The Council maintained that the ADC remains committed to peaceful, issue-based political engagement, insisting that its campaign is focused on addressing the country’s pressing challenges, including hunger, insecurity, unemployment, corruption and what it described as the failures of the Tinubu administration.

It accused the APC of resorting to violence because it had little to offer Nigerians in terms of credible solutions to the country’s problems.

Consequently, the ADC-PCC demanded that President Tinubu immediately and publicly withdraw his “All Is Fair in Politics” remark, condemn and call to order APC governors and party officials accused of inciting violence, and direct security agencies to protect all Nigerians impartially rather than allow them to become instruments of intimidation and oppression against opposition parties.

” Nigeria belongs to all of us. No political ambition is worth the blood of any Nigerian.
“If former President Goodluck Jonathan could make that profound declaration in 2015, President Tinubu has no excuse not to say so and demonstrate the sincerity of his commitment to peace in 2026.

“The ADC will not be intimidated. We will continue to campaign peacefully, and in 2027, Nigerians will have the opportunity to vote for competence, integrity and a new beginning,” the statement added.

Continue Reading

Trending

Copyright © 2023 Thebigeye